Agenda Item #36 Title Approval of Professional Support Center - Sitework Improvements - Change Order 1 - Final - Agreement Between Owner and NDC Construction Company - p.48 Executive Summary The purpose of the requested action is to approve Change Order 1 - Final to the Agreement between Owner and NDC Construction Company, which deducts the unexpended unforeseen conditions funding and decreases the Guaranteed Maximum Price to close out the project. The Superintendent recommends approval of Recommendation Motion and approval of Financial Impact The amount of Change Order 1 - Final is ($501.82). The Guaranteed Maximum Price for the Professional Support Center - Sitework Improvements, including this Change Order 1 - Final, is $267,143.18, and is included in the total project budget of $400,000.00. Contact Department of Construction Services SJD/JAD/pm 07/27/09 Attachment: PSC Sitework Improvements Summary Sheet.pdf Attachment: PSC Sitework Improv CM CO 1 Final 072709.pdf |